Saturday, July 31, 10:00 AM to 2:00 PM.
There are 4-5 major tasks that need to get accomplished.
There are 4-5 major tasks that need to get accomplished.
- Digging several thickened footings, placing rebar- Installing insulation and plastic around foundation- Backfill around the plumbing- Placing wire mesh in position- Securing elevator shaft for safety
Vision House will provide 1-2 general supervisors and of course, lunch is included! RSVP to Kristis@vision-house.org or call 425-228-6356.